On a new building or a tenant build-out, the sprinkler contractor is one trade among many, and the schedule lives or dies on coordination. We take work as a subcontractor to general contractors, and the sequence is consistent from project to project. Submittals go in first: shop drawings, hydraulic calculations, and product data for the architect, engineer, and fire marshal. Rough-in follows the framing and ductwork, with the pipe coordinated against lighting, HVAC, and ceiling grids so heads land where the reflected ceiling plan needs them.
Before the ceiling closes, the piping gets its hydrostatic test, generally 200 psi for two hours, with the fire marshal's inspector witnessing. After finishes, heads get trimmed, the flow and tamper switches get tied to the alarm, and the acceptance test runs. The handoff is a clean package: as-built drawings, test certificates, operation and maintenance information, and the signed acceptance paperwork. If you are a builder looking for a sprinkler and alarm sub, see our general contractor subcontracting page, and if you install for a national integrator, our integrator installation partner page explains how that works.